DFCU Project, HRRL

Rajasthan, India

Sector : Oil & Gas

A Project By VRC

Precast Civil Works pertaining to DFCU Project, HRRL

The Precast Civil Works pertaining to the DFCU Project of the HRRL (Hindustan Petroleum Corporation Limited Rajasthan Refinery Limited) was a prestigious project executed by VRC Construction India Ltd. The project was carried out under the supervision of L&T Hydrocarbon Engineering Limited and HRRL.

The project had a total bidding value of 39 crores and was initiated on 22nd July 2021. VRC Construction was successful in completing the project within the specified timeline, with the final completion date being 30th September 2022.

The Precast Civil Works were a critical aspect of the DFCU Project and involved the use of precast concrete components in the construction of various structures. Precast concrete offers numerous benefits, including faster construction times, improved quality control, and reduced waste.

VRC Construction has a wealth of experience in executing projects of this nature, and its expertise in the precast civil works was evident in the successful completion of this project. The company’s commitment to quality, safety, and timely delivery was evident throughout the project, and it demonstrated its capability to deliver large-scale projects within challenging timelines.

In conclusion, the Precast Civil Works of the DFCU Project at HRRL was a landmark project executed by VRC Construction India Ltd. The project was carried out to the highest standards, and its successful completion demonstrates the company’s expertise in the field of precast civil works and its commitment to delivering projects of the highest quality within challenging timelines.

Name of the ProjectPrecast Civil Works pertaining to DFCU Project, HRRL
Name of the ClientL&T Hydrocarbon Engineering Limited/ HPCL Rajasthan Refinery Ltd. (HRRL)
Work Executed ByVRC Constructions India Ltd.
LocationRajasthan
Construction Cost (in INR)39 Crore
SegmentCivil Construction
SectorPublic
Construction Start Date22.07.2021
Construction Completion Date30.09.2022
Latest StatusCompleted