Rajasthan, India

As part of a critical border infrastructure strengthening initiative under the Central Public Works Department (CPWD), VRC Group has been awarded the prestigious project for the Replacement of Old Damaged Fence by New Design Single Row Fence in the AOR of Sri Ganganagar Sector, Rajasthan.
Spanning an extensive length of 157.204 kilometres, this project plays a vital role in enhancing border security infrastructure through modernised fencing systems engineered for durability, surveillance compatibility, and long-term operational resilience.
The contract has been awarded in Engineering, Procurement and Construction (EPC) Mode-III, with a total execution timeline of 600 days, commencing as per the Letter of Acceptance dated 19.02.2025.
This large-scale border infrastructure project involves dismantling aged and damaged fencing systems and replacing them with a newly designed Single Row Fence system tailored to current strategic and structural standards. The scope encompasses engineering design validation, procurement of high-grade materials, fabrication, transportation, installation, and commissioning of the fencing infrastructure across challenging terrain conditions.
The project reflects VRC Group’s capability in executing time-bound, security-sensitive government infrastructure assignments with precision, compliance, and operational excellence.
Installation of a new design Single Row Fence system engineered for enhanced durability, structural strength, and long-term performance under varying environmental conditions.
Comprehensive responsibility covering design coordination, material procurement, quality control, logistics management, and on-site execution within defined timelines.
Upgrading legacy fencing infrastructure to modern standards, ensuring improved surveillance integration and fortified perimeter protection.
Delivering the project within the stipulated 600-day timeframe, maintaining stringent quality benchmarks and optimising resource deployment.
The Sri Ganganagar Border Fencing Project stands as a significant milestone in VRC Group’s expanding portfolio of high-value government infrastructure projects. Executed under EPC Mode-III, this assignment reinforces VRC’s expertise in delivering large-scale, security-critical infrastructure with efficiency, engineering precision, and adherence to national standards.
By contributing to the modernisation of border protection systems, VRC Group continues to play a responsible role in strengthening India’s strategic infrastructure backbone.
Name of the Project | Replacement of Old Damaged Fence by New Design Single Row Fence in the AOR of Sri Ganganagar Sector, Rajasthan |
Name of the Client | Central Public Works Department (CPWD) |
Starting Date | As per the LOA (19.02.2025) |
Completion Date | 600 Days |
Work Executed By | VRC Group |
Location | Sri Ganganagar Sector, Rajasthan, India |
Construction Cost (in INR) – Estimated Amount | ₹3,90,72,83,889.00 |
Tendered Amount (in INR) | ₹2,93,00,72,188.00 |
Segment | Infrastructure Development |
Sector | Government Construction / Public Infrastructure |